1. f samples of 100 for a process are taken and p is 0.15, the upper and lower control limits for a 3-sigma p-chart are
a |
UCL = 0.322, LCL = 0.000 |
b |
UCL = 0.190 , LCL = 0.010 |
c |
UCL = 0.257, LCL = 0.043 |
d |
UCL = 0.045, LCL = 0.005 |
2.
In an Excel spreadsheet for a p-chart, if the total
number of defectives for 20 samples of 100 observations each is in
cell F26, the Excel formula for p is
a |
=((F26)*(20))/100 |
b |
=((F26)*(100))/20 |
c |
=(F26)/(20) |
d |
=(F26)/((20)*(100)) |
3. In an Excel spreadsheet for a c-chart, if the
population process average for 20 samples, c, is in cell
H4, the Excel formula for the upper control limit is
a |
=H4+SQRT(3*H4) |
b |
=H4+3*SQRT(H4) |
c |
=H4+3*SQRT((H4*(1-H4))/(100)) |
d |
=H4+3*SQRT(H4/20) |