19) 6 10 BO) co ка 1) A project is modelled by the activity network shovn above. Theactivitiesare represented by the arcs. The number in brackets on each arc gives the time, in hours, to camplete the activity. The numbers in cincles are the event numbers. Each activity req uiresone wodker. a Explain the purpose of the dotted line from event 6 to event 8 b Calculate the early time and late time for each event c Calculate the total float on activities D, Eand R d Determine the critical activities.