2 & 14. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 2 with an imposed finish date of 23 and then 29 days.

Activity

Duration

IPA

ES

EF

LS

LF

TF

FF

A

7

-

B

10

-

C

15

A

D

8

A, B

E

4

C, D

Solution by an expert tutor