Question: 2 determine the schedule variance cost variance spi cpi and...

Question details

2. Determine the schedule variance, cost variance, SPI, CPI, and CSI for a project that has an actual cost at month 12 of $100,000, a scheduled cost of $120,000 and an earned value of $80,000.