3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 3 with an imposed finish date of 15 and then 20 days.

Activity

Duration

IPA

ES

EF

LS

LF

TF

FF

A

2

-

B

4

A

C

6

A

D

9

A

E

5

B

F

7

B, C

G

3

D, E, F