Question: 5 amp 17 for the following schedule draw the node...

Question details

5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 5 with an imposed finish date of 26 and then 35 days.

Activity

Duration

IPA

ES

EF

LS

LF

TF

FF

A

6

-

B

2

-

C

9

-

D

4

A, B

E

7

B

F

5

D

G

10

D, E

H

8

C, F, G

I

3

C, G

J

2

H, I