Question: a methods and measurements analyst needs to develop a time...

Question details

A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results:

Observation 1 2 3 4 5
Time (secs) 95 74 75 80 80

What is the standard time for this task if the employee worked at a 26 percent faster pace than average and an allowance of 21 percent of the job time is used?

(Keep one decimal place in your answer)