Question: a project requires the intial fixed capital outlay of 200000...

Question details

A project requires the intial fixed capital outlay of $200,000 and net working capital of $50,000 before it starts. The project manager forecasts that the annual sales to be $350,000 until the project ends in the next five years. The annual cash operating expense is $230,000. The fixed assets should depreciate based on double declining method to no salvage value. At the end of the project, the fixed assets can be sold at $6,000. With the tax rate of 30%, what is project NPV?