Activity   A B C D E F G H
Time 5 3 7 6 7 3 10 8

CH Finish Start

  • Identify the critical path.
  • How much time will be needed to complete this project?
  • Can activity D be delayed without delaying the entire project? If so, by how many weeks?
  • Can activity C be delayed without delaying the entire project? If so, by how many weeks?
  • What is the schedule for activity E?