1. Engineering
  2. Civil Engineering
  3. complete the following precedence diagrams identify the critical path 1...

Question: complete the following precedence diagrams identify the critical path 1...

Question details

Complete the following precedence diagrams. Identify the critical path.

1.

Activity ESI Dur LS EF FFITF (LF Set support beam Mobilize Remove siding Set rafters Install roof Move out 4 4 2 Install wind

2.

Call inspector Inspect repair 2 Night lights Traffic control 2 Mobilize Finish work 2 Set barricades pavement Cut Repair leak

3. Problem 3: As a good scheduling practice, add a “Start” activity and a “Finish” activity box. For this precedence diagram, “Slack” is Total Float.

Early Start Durati on Early Finish Task Name Late Start Slack Late Finish e. 28

Solution by an expert tutor
Blurred Solution
This question has been solved
Subscribe to see this solution