Question: cpm activities s and t must be completed before activity...

Question details

CPM Activities S and T must be completed before activity U can be started. The duration for S, T, and U are 24, 22, and 49 days, respectively If the latest finish time for U is at the end of day 171 then the latest start time for T is at the end of day