Question: embassy club condominium located on the west coast of florida...
Question details
- Embassy Club Condominium, located on the west coast of Florida,
is undertaking a summer renovation of its main building. The
project is scheduled to begin May 1, and a September 1 (17 week)
completion date is desired. The condominium manager identified the
following renovation activities and their estimated times in the
table below:
- Using the data in the above statement and in the table below to
answer the following questions:
- Draw a project network.
- What are the critical activities?
- What activity has the most slack time?
- Will the project be completed by September 1?
- Using the data in the above statement and in the table below to
answer the following questions:
Activity |
Immediate Predecessor |
Time |
A |
- |
3 |
B |
- |
1 |
C |
- |
2 |
D |
A, B, C |
4 |
E |
C, D |
5 |
F |
A |
3 |
G |
D, F |
6 |
H |
E |
4 |
- Provide a brief narrative on your CPM and describe the importance of the use of this tool for business and industry.