1. Business
  2. Operations Management
  3. for the given problem predecessor time time normal crash normal...

Question: for the given problem predecessor time time normal crash normal...

Question details

For the given problem, Predecessor Time Time Normal Crash Normal Crash Cost Cost 3 3 60 60 7 6 30 80 5 2 50 90 30 50 B,C 2 40 100 Answer the following questions: 0 What is the normal cost of the project? [Select ] ( Which activity would you crash frst to crash the project by one day and what will be its cost? (i) What is the approximate cost to crash by an additional day? ISelect )
Solution by an expert tutor
Blurred Solution
This question has been solved
Subscribe to see this solution