  3. given the project within the table below calculate the following...

Question: given the project within the table below calculate the following...

Question details

Given the project within the table below, calculate the following: DurationImmediate hours) Predecessors None None 10 None 7 B,C A,F a. What is the projects minimum completion time? [Select ] b. What is the critical path in the project? Selectl c. What is the slack in activity B? ISelect] ISelect l d. What is EST and LST for Activity A?