Question: gmt5433 operations management sp19 brytani sykes amp 2219 1108 a...

Question details

GMT5433 Operations Management SP19 Brytani Sykes & 2/2/19 11.08 A omework: HW 5 (30) core: 0 of 1 pt 1 of3 (0 complete) HYV Score: 0%, 0 of 5 roblem 2 Question Help A process currently services an average of 54 customers per day. Observations in recent weoks show that Rs uization is about 90 percent, allowing for just a 10 percent capacity cushion Itf demand is expected to be 60 percent of the current level in five years and management wants to have a capacity cushion of just 3 percent what capacity requirement should be planned? The needed capacity roquirement is customers per day (Enter your response rounded up to the next whole number) Enter your answer in the answer box and tmen click check Answer Type here to search