Question: if a project has an expected average completion time of...

Question details

If a project has an expected (average) completion time of 18 and standard deviation of 1.71, what due date should the team set if they want to be 99% sure that they will complete the project on time? Note: Only round your final answer to 2 decimal places. Your Answer Answer