Question: in the following table for building new motels time weeks...

Question details

in the following table for building new motels Time (weeks) Time (weeks) Immediate Activitym b Predecessorts) Activitym b Predecessor(s) 9 12 B 1 823 C 9 14 16 4 7 12 D, G, H I, J 9 20 C, E a) The expected (estimated) time for activity Cis 13.50 weeks (Round your response to two decimal places.) b) The variance for activity C is weeks. (Round your response to two decimal places)