  1. In the following table task durations are given in weeks. Use the three point to find:

Activity

Predecessor

Optimistic

Normal

Pessimistic

A

None

2

4

6

B

None

3

5

9

C

A

4

5

7

D

A

4

6

10

E

B,C

4

5

7

F

D

3

4

8

G

E

3

5

8

  1. Construct the (AON) Activity on Node network diagram
  2. Find each activity’s ES, EF, LS and LS
  3. Identify all paths. Which path is the critical path?
  4. Calculate the slack for each activity.
  5. How long will it take to complete the project?