In the following table with the activity of the precedence sequence and expected time (days) are listed for a project:
Activity Immediate Predecessors Time (days)
A - 7
B A 2
C A 4
D B 5
E B 5
F C 5
G E,F 2
H D 3
I G,H 7
a.) The activities on the critical path are: __________
b.) The project length is _______ days.