Question: just need help calculating the probability...

Question details

Activity a m b Predecessor(s)Activity a 12 bPredecessor(s) C, E 8 24 8 12 1 14 4 D, G, H 4 20 C, E a) The expected (estimated) time for activity C is 12 weeks. (Round your response to two decimal places.) b) The variance for activity C is 1.78 weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is A - B-E-F- H-J- K d) The estimated time for the critical path is 41.5 weeks. (Round your response to two decimal places.) e) The activity variance along the critical path is 22.97 weeks. (Round your response to two decimal places.) f) The probability that Hopkins Hospitality will finish the project in 36 weeks or less is(Enter as a probability and round your response to three decimal places)just need help calculating the probability.

Solution by an expert tutor
Blurred Solution
This question has been solved
Subscribe to see this solution