Question: please show all work no excel btw the answer is...

Question details
Please show all work! No excel! Btw the answer is not 11!!


Six tasks are needed to process a certain product. The following table provides the information about the tasks. What is the shortest cycle time that will permit using exact two workstations (need to assign these six tasks into two workstations)? Task Task Time (in minutes) Predecessors None 4 None A,B 4 D,E 4 4 O 12 0 5 o 10