Problem 2 (20 points) ng factory is using batch production to manage its production operations. Knowing that the estimated scrap rate of the machining process is 3%, it was decided that 65 good parts should be produced from each batch. During the machining process it is important to change the SR20 cutting tool each 15 part. The tool changing time 2 min. The machining time for each part-3 min, handling time = 2 min, and the setup time for the machine-1hr. If the starting work part costs SR10 and the labor and equipment hourly rate included overhead SR150. Determine (a) The production rate of good parts (b) The cost of finished good part Problem 3 (20 points)