Question: problem 4 assume you have a project with ten activities...

Question details

Problem 4 Assume you have a project with ten activities labeled A through J. Derive the earliest expected completion time (TE), latest expected completion time (TL), and slack for each of the tasks (begin at time = 0). A) Complete the missing values in the table B) Draw a network diagram and show the critical path Activity Preceding event Duration TE TL Slack Critical Path?

activity preceding event duration Te Tl Slack Critiacl Path
A ----- 4
B A 5
C A 6
D A 7
E A,D 6
F C,E 5
G D,E 4
H E 3
I F,G 4
J H,1 5