Problem 4 Assume you have a project with ten activities labeled A through J. Derive the earliest expected completion time (TE), latest expected completion time (TL), and slack for each of the tasks (begin at time = 0). A) Complete the missing values in the table B) Draw a network diagram and show the critical path Activity Preceding event Duration TE TL Slack Critical Path?
activity | preceding event | duration | Te | Tl | Slack | Critiacl Path |
A | ----- | 4 | ||||
B | A | 5 | ||||
C | A | 6 | ||||
D | A | 7 | ||||
E | A,D | 6 | ||||
F | C,E | 5 | ||||
G | D,E | 4 | ||||
H | E | 3 | ||||
I | F,G | 4 | ||||
J | H,1 | 5 |