Question 1 (1 point) The City of Toronto is building a new park that must be completed 45 weeks from inception. The expected completion time of the project (average) is 39 weeks and the activities along the critical path of the project have the following variances: Variance 3.12 2.67 7 Activity .96 What is the probability that the project will be completed on or before the 45 week deadline?