The following process model represents part of a IT support process.

Assume the following minimum times required for each activity in the above diagram.
Activity | Time (minutes) |
---|---|
Submit request form | 15 minutes |
Save request | 20 minutes |
Notify Support Engineer | 15 minutes |
Obtain software license | 5 minutes |
Create installation script | 10 minutes |
Mark complete | 5 minutes |
Notify User | 5 minutes |
Close request | 5 minutes |
Given the above minimum required times, what is the shortest possible time that the entire process could take (in minutes)?
Solution by an expert tutor