Question: review the graph showing the contractors estimate at completion eac...

Question details

Review the graph showing the contractor's estimate at completion (EAC) for the armament Work Breakdown Structure (WBS) element, along with the Government's optimistic (best case) and pessimistic (worst case) EACs. Based on the graph, does the contractor's EAC appear to be reasonable?Pessimistic EAC $7.5M Optimistic EAC Contractors EAC 2015 2014 2013

(IMAGE DESCRIPTION: EAC chart, with dollars in the millions. Pessimistic EAC is $7.5M, Optimistic EAC is $5.7M, and Contractor's EAC is $5.0M.) *

Yes, the contractor?s EAC is below the optimistic EAC calculated by the Government.

It is not possible to tell from the graph where the contractor?s EAC falls.

No, the contractor?s EAC is below the range of EACs calculated by the Government.

No, the contractor?s EAC is above the pessimistic EAC calculated by the Government.