Rodger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity Immediate Precessdors Times (days)
A - 10
B - 5
C - 1
D B 2
E A,D 5
F C 6
G E,F 8
a.) The project length for the leadership training program development project = ____ days.
b.) Slack time for each of the activities is:
Activity Slack time
A _________
B ________
C _________
D _________
E __________