1. Business
  2. Operations Management
  3. roger ginde is developing a program in supply chain management...

Question: roger ginde is developing a program in supply chain management...

Question details

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activity Immediate Predecessor(s) Time (days) 4 1) 10 A, D E, F 12

This exercise contains only parts b, c, and d.

b) The critical activities for the leadership training program development project are________

c) The project length for the leadership training program development project =_____days.

d) Slack time for each of the activities is:

Solution by an expert tutor
Blurred Solution
This question has been solved
Subscribe to see this solution