Table 11-7

A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries. The remaining legible entries are correct.

Activity

Predecessor

Duration

ES

EF

LS

LF

Slack

A

--

B

A

12

12

C

A

5

18

D

B

8

E

C

9

0

F

D,E

27

34

0

G

E

6

33

1

H

F,G

34

40

4) Consider the project summarized in Table 11-7. What is the early finish time for Activity D?

A) 19

B) 20

C) 21

D) 22

Please show me step by step on how to get this. Thanks!