Question: the activities needed to build a prototype laser scanning machine...

Question details

The activities needed to build a prototype laser scanning machine at Generic Corp are listed in the following table. Answer the questions that follow: Immediate Activity Time (weeks) Predecessor C.E D,F a. What is the length of the critical path? [Select] b. What activities are on the critical path? ISelect] c. How much slack is in activityHSelect] d. What is the EST and LST for activity E? [Select ] weeks