Use Excel and/or Computer Software/QM.

A. The Hardrock Concrete Company has plants in three locations and is currently working on three major construction projects, each located at a different site. The shipping cost per truckload of concrete, daily plant capacities, and daily project requirements are provided in the table below.

FROM\TO Project A Project B Project C CAPACITY
PLANT 1 $10 $4 $11 70
PLANT 2 12 5 8 50
PLANT 3 9 7 6 30
REQUIREMENT 40 50 60


REQUIRED:

i. Formulate this as a linear program to determine the least cost way to meet the requirements.
ii. Then Solve the problem using any computer software (and show the total cost).  