  3. using the data below create the project schedule using normal...

Question: using the data below create the project schedule using normal...

Question details
  1. Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days, and so on until is in all crash mode. Identify how much it would cost for each day you crash the schedule.

Activity

Predecessor

Normal Time

Normal Cost

Crash Time

Crash Cost

Crash Cost per Day

A

12

200

9

350

B

A

8

300

8

300

C

A

9

250

7

450

D

B

6

400

5

600

E

B, C

5

150

4

225

F

C

10

500

9

650

G

D, E, F

8

400

6

900