What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?

Normal Crash Time Normal Total Cost Activity Time (days) (days) 4 Cost $800 $300 $600 $750 $1,200 with Crashing Immediate Predecessor(s) $1,100 $400 $650 $1,500 $1,650 4 4

By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers. )

Each Activity Should be Reduced BY Activity

The total cost of crashing the project by 4 days is $_________ (Enter your response as a whole number. )